How to deliver a transformative urgent treatment centre in 72 weeks
Client
University Hospitals Plymouth NHS Trust
Services
Project management, employer’s agent, quantity surveying, cost management
Stages
RIBA Stages 2–5
Partners
Hulley & Kirkwood, Stride Treglown
72 weeks
From start on site to first patient
~100+
Patients treated every day
140,000 kWh
Generated each year by on-site solar
BREEAM
Very Good and EPC A targeted
Project overview
A new three-storey outpatient facility, delivered on a live hospital site.
Since 2024, we have supported University Hospitals Plymouth NHS Trust with the delivery of the Dartmoor Building at Derriford Hospital. Our team provided project management, employer’s agent, quantity surveying and cost management services, helping to deliver a critical healthcare project within a highly complex, live hospital environment.
The facility includes
Urgent Treatment Centre
Fracture Clinic
Main Outpatients Department
Pre-operative Assessment
On-site X-ray facilities
Dedicated treatment rooms

The project in detail
From challenge to outcome

01
The challenge
Building next to a Major Trauma Centre
The Dartmoor Building was delivered on the live Derriford Hospital site, a Major Trauma Centre serving Devon and Cornwall. Construction sat close to sensitive clinical departments and critical access routes, so patient safety, emergency access and uninterrupted clinical operations had to be protected throughout a compressed programme.

02
Our approach
Structured governance, controlled logistics
We put a proactive, structured approach in place to protect live hospital operations. Weekly progress meetings, decision logs and cost reviews kept governance tight, while careful sequencing of deliveries and road closures maintained access to critical departments. Regular workshops kept clinical, estates and operational teams aligned.

03
The impact
Urgent care, fractures and outpatients under one roof
The building hit its target first patient date and now treats around 100 patients a day. Urgent care, fractures and outpatient services are brought together in one modern setting, relieving pressure on existing facilities and supporting the future development of the hospital’s Emergency Care facilities.

04
Sustainability & social value
Low-carbon by design, local by default
Air-source heat pumps, photovoltaic panels and biodiversity enhancements support the Trust’s sustainability goals, with the building targeting BREEAM Very Good and EPC A. Social value included local supply chain involvement, student engagement, work with Southwest Women in Construction and dementia-friendly design.
“
The Dartmoor Building sets a new benchmark for healthcare delivery at Derriford Hospital, combining design quality, programme certainty and strong stakeholder coordination in a live hospital environment.
Project outcome
Lessons learned
What this project taught us about live hospital delivery
01
Define the brief early
Reduce risk and avoid costly rework later in the programme.
02
Engage stakeholders first
Especially where clinical and operational requirements are complex.
03
Keep governance clear
Decision logs and escalation routes keep everyone moving together.
04
Plan for the unexpected
Contingency strategies for programme-critical infrastructure.